Who coordinates the existing solar system?
On one Hercules project, the original roof estimate excluded solar removal and reinstallation. ARS later obtained an electrician’s option while the homeowner checked with the existing solar provider. March 2026 correspondence says the roofing permit had been obtained so that provider could begin its solar-permit process. ARS then checked the removal timing before grouping the roof with another Hercules job. The roof work proceeded to a material order and invoice; municipal final approval is not confirmed.
This sequence explains the practical dependency: a roof start needed to fit the panel-handling work, and responsibility was divided between parties. For another project, identify who arranges removal, who deals with the provider and who is responsible for storage and reinstallation before fixing the tear-off date. The recorded sequence is project experience, not a universal City solar-permit order or a claim of certification by a particular provider.